is a grassroots non-profit using science and activism to tackle climate change and reduce hazards to public health and the environment from nuclear power and other polluting electricity production, and working for a transition to safe, economical energy in North Carolina.

 

 

Please support our work with a tax-deductible membership
Donate Now Through Network for Good

 

          

NOTE TO EDITORS                                                                                     

January 22, 2007                                                                                                             

Duke Energy uses dubious deadline to push Commission –
despite coal plant’s latest price surge toward $4 billion

Summary of Three-Day (January 17-19, 2007) Hearings Before the NC Utilities Commission:

Durham, NC – In a bid to salvage a wounded project with a soaring price tag and widespread opposition, Duke Energy CEO Jim Rogers closed out three days of hearings with an aggressive sales pitch to the NC Utilities Commission late Friday.  Duke’s senior officials earlier admitted they could better determine price estimates for the Cliffside plants – and the analysis that would prove them the best option – within a few months.  But Rogers, while frequently contradicting himself, his senior officials and the facts of the case, pressed commissioners to trust his professional judgment and rapidly approve the two 800 megawatt coal burners.  Key points from formal testimony and cross examination:  

Rising and Uncertain Costs:  The latest cost overrun was exposed on day one of the hearings after public interest attorneys found that a $1 billion increase announced in December did not include finance costs of the project that could send the price tag to $4 billion.  Rogers’ pre-filed testimony also had stated the price tag as $3 billion, without mention of the finance costs.  His officials admitted those costs would be hundreds of millions, and that market forces are creating substantial uncertainties about the costs of coal and nuclear plants.  Rogers said that if ever built, nuclear plants will cost 45% more than prices cited by Westinghouse.

Questionable Deadline – Watch for More Hikes:  Duke Energy is aggressively pressing for swift Commission approval, citing without support a February deadline to lock in contracts that constitute only 25% of the total price.  However, Duke admits that it does not have firm bids on 75% of project cost items, but said the corporation had tried to reflect anticipated increases in those items in the latest total estimate.  Duke has an incentive to provide low estimates of those costs until after the Commission approves the project.  Also, Duke and its vendors all have reason to appear inflexible regarding the February deadline. Casting further doubt on this rush for Commission approval is the fact that Duke has not begun a months-long public process to obtain a state air pollution permit.  Construction must await that permit, and presumably Duke would not commit to equipment contracts worth billions of ratepayer dollars until that time.  As to Rogers’ warnings about NC running out of power, Duke admitted it plans to build gas-fired peaking plants anyway, which could prevent any short-term gap between supply and demand.

Uncontrolled Greenhouse Gases for Decades:  Despite Rogers’ aggressive public relations calling for climate protection, he admitted he wants the two huge Cliffside plants exempted from upcoming carbon regulations.  If he were to lose that gamble, rates will rise even more in the short run.  Rogers believes there might be a technology in 15 or 20 years to remove the greenhouse gases from the smokestacks.  An earlier witness for Duke said that if such technology is ever developed, it would be extremely expensive. 

Maximum Sales and Profits:  Under cross examination, Rogers claimed his only motivation is customer service, insisting he had not even considered, nor knew the amount of, the key financial benefits of the project for his corporation: the revenue impacts of adding up to $4 billion to the rate base, along with a guaranteed mark-up and profit.  Are we to believe that Duke Energy’s board of directors and financial managers never asked about the financial benefits of the project?   

Didn’t Consider Efficiency:  Despite a public posture assertively lauding energy efficiency (including a state “stakeholder” process that Duke now says might be delayed until 2008 according to Duke’s Janice Hager), Duke didn’t include efficiency in any modeled scenarios for upcoming electricity needs.  Hager admitted the corporation could complete the modeling to include efficiency and other omitted factors within a few months and at low expense.  But she insisted that 101 megawatts (one-sixteenth of the Cliffside expansion) is the total potential for efficiency over the next 35 years.  Later, Rogers boasted of his dedication to efficiency, but layered qualifiers over various “commitments” to the Commission.  A national energy efficiency taskforce that Rogers co-chairs recently called for ramping up power-saving programs in the next three years, but Rogers said his own company cannot be expected to comply with that initiative.

Cliffside Fails the Least Cost Requirement:  After learning of the first billion-dollar overrun in October, within 24 hours Duke determined Cliffside is still the best option.  It doesn’t meet the “least cost” requirement under state law, but Rogers argued it meets his “best cost” judgment.  But with coal and nuclear costs increasing at an uncertain rate, surely the Commission should order Duke to model Cliffside compared to efficiency and renewable energy – the costs of which are decreasing dramatically.

Customers to Take the Risk:  Rogers made clear that he wants Cliffside and all plants to fall under proposed legislative changes that would force customers to pay up front – plus a utility mark-up – for new plants, even if they’re cancelled and regardless of cost overruns.  He’ll promote “CWIP” as a way to reduce finance costs, but in fact, it would only shift even more of the costs and risks to the public.    

A So-called Public Staff:  Knowing his case was in trouble, Rogers’ began his testimony to the Commission with an ad lib thanking the Commission’s Public Staff for “supporting us” on the expansion.  Later, he admitted under cross examination that the Public Staff – an agency that is supposed to be independent and represent the public’s interests – had endorsed Duke’s plan before the hearings, i.e. before listening to the debate, expert testimony, cross examination and questions by Commissioners.

Late in his three-hours on the stand, Rogers’ true colors trumped his $4 billion smile.  His dramatic charm-laden performance turned into a finger-pointing rant toward the environmental attorneys, denouncing the five intervener groups for opposing new power plants, belittling the advantages of clean energy, and serving notice:  “We intend to work with others to incent building large power plants in this state!” 

Rogers’ approach seems to be “damn the torpedoes.”  He talks about small, uncertain concessions to energy efficiency, largely as public-relations cover for new plant construction.  If he succeeds, it will jeopardize the state’s economy, prevent the infusion of thousands of clean-energy jobs, and continue a sorry record of corporate influence over North Carolina decision-makers.  No rational, democratic society should allow such a course, which would also keep us speeding into the abyss of climate change.

In the 1970s, the public warned the Utilities Commission it should focus on energy efficiency, but it didn’t listen.  So the power companies wasted 100s of millions of ratepayer dollars on plants that were never finished due to cost overruns and lack of demand.  The plants it did build caused an incalculable cost in health damage and greenhouse gases.  The Commission must not repeat that mistake, which could lock this state in last century’s energy technology as much of world moves ahead.

With billions of public dollars at stake and the first large plant in 30 years, the commissioners should not let themselves be bullied into moving ahead quickly without all information needed for this vitally important decision.  As Commissioner Jim Ervin asked, “Why shouldn’t the Commission insist all the work be done?”

##

Advocating for the public interest were attorneys for Southern Environmental Law Center, NC Sustainable Energy Association, Environmental Defense, Southern Alliance for Clean Energy, NC WARN, Attorney General’s office, Carolina Utility Customers Association, and private citizen Wells Eddleman.

NC WARN  PO Box 61051 Durham NC  27715-1051 919 416-5077  ncwarn@ncwarn.org   www. ncwarn.org

 

Contact NC WARN:

North Carolina Waste Awareness and Reduction Network
P.O. Box 61051, Durham, NC  27715-1051
Ph: (919) 416-5077     Fax: (919) 286-3985


Unsubscribe from NC WARN Email