|
PO Box 61051
Durham, NC 27715-1051
Phone: (919) 416-5077
Fax: (919) 286-3985
ncwarn@ncwarn.org www.ncwarn.org
|
Waste Awareness and
Reduction Network
NC WARN
|
NEWS RELEASE Contact: Jim Warren
April 20, 2006 919-416-5077
Shearon Harris Near-Miss Ties for Worst Since
Three Mile Island
Emergency
core cooling system was “seriously degraded” for a year, greatly increasing reactor
risk in early 1990s. Group demands more openness.
DURHAM, NC – A year-long,
high risk condition at the Shearon Harris nuclear plant has been uncovered
by a nuclear watchdog in Washington after remaining secret for 15 years. A design flaw in the reactor’s emergency
cooling system caused valve and pipe failures that rendered the system inoperable, and unable to respond if called on to
prevent a meltdown. The problem went
unnoticed until a refueling outage in 1991.
This “precursor event” to a
nuclear accident ranks among the highest risk incidents in the U.S. since the 1979 partial meltdown at Three Mile Island, according to Nuclear Regulatory Commission criteria.
Agency investigators concluded: “The flow rate of water required
to neutralize the effects of ‘design basis’ accidents assumed in the licensing
analysis would not have been attained.” (emphasis
added)
The discovery was made by
Greenpeace’s Jim Riccio while conducting research for a report to be released
Monday on U.S. nuclear accidents and near-misses since the 1986 Chernobyl disaster. The
Harris failure stemmed from a flaw by plant designer Westinghouse. After Westinghouse alerted several nuclear
plants about the defect, Harris owner CP&L attempted to correct the
problem, but unknowingly made it worse.
Riccio noted that NRC
calculated the year-long Harris failure as having the same risk for a meltdown
as did the 2002 near-miss at Ohio’s Davis Besse plant, when a large hole was discovered
in the reactor vessel. The NRC calculated the Harris failure as increasing the risk of a reactor meltdown by
up to 1,000 times over normal. If a
rupture in primary cooling system valves or pipe connections had occurred
during that year, the emergency cooling system would have been triggered, but
unable to protect the reactor core from overheating and releasing large amounts of radioactive materials.
Durham-based watchdog group NC WARN said today the discovery was further indication that Progress Energy needs to be more open with the public
about problems and how the utility is correcting them. “This is dramatic evidence that major system failures do occur at nuclear plants,” said Jim Warren,
Executive Director of NC WARN. “It
shows that the utilities and NRC do not have everything under control, and that
they gamble on the public not finding about these problems – instead of
explaining them.”
Warren also questioned why the system failure persisted for
a full year without CP&L rechecking the correction it had made after
Westinghouse alerted them about the defect.
NC WARN has detailed other Harris design flaws that have remained uncorrected for years, according to Warren. Next week,
the group will publish a report on serious and ongoing safety problems at
Harris, along with other reasons Progress should abandon plans for new reactors
at the southeastern Wake County plant.
CP&L was recently renamed
Progress Energy, and in January selected Westinghouse to possibly build two
more reactors at Harris.
Westinghouse is still altering its new design in an effort to entice some utility to build a new plant and revive the fading industry. “Cost-cutting pressures are pervasive in
this industry,” said
Warren.
“This near-miss is another reason the public and local governments
should not be shut out
during the licensing process for new
reactors.”
Union of Concerned
Scientists’ David Lochbaum, a technical advisor for NC WARN, said the Harris
failure further belies industry claims of being safer over the years “just
because they haven’t melted down another reactor since Three Mile Island.” He said there’s a common misconception that only explosions, such as the Chernobyl disaster, can lead to large releases of
radiation. During a reactor or steam
generator accident, high pressure inside the containment building can last for
hours or days, which would push large amounts of radioactive gases through
scores of openings and seals in the building’s walls.
NC WARN has urged Progress
for years to be more forthcoming about problems at its plants – and whether they
are being corrected – instead of the watchdog group and its allies having to
discover and expose them.
“Public safety shouldn’t depend on cat
and mouse games about problems, nor on watchdog groups having to dig out
information from NRC’s Byzantine data system where everything is
written in nukespeak,” added Warren. “We
call on CEO Robert McGehee to instruct his people to be forthcoming about problems that arise, and whether and how
they are being corrected. And we want to
know what other skeletons there might be in the Shearon Harris closet.”
##
NC WARN is a member-based,
grassroots non-profit using science and activism to tackle climate change and
reduce hazards to public health and the environment from nuclear power
and other polluting electricity production, and working for a transition
to safe, economical energy in
North Carolina.