is a grassroots non-profit using science and activism to tackle climate change and reduce hazards to public health and the environment from nuclear power and other polluting electricity production, and working for a transition to safe, economical energy in North Carolina.

 

 

Please support our work with a tax-deductible membership
Donate Now Through Network for Good

 

NEWS RELEASE                                                                                          
April 29, 2003
Contact:  Jim Warren                                                                                                                 
919-416-5077

NC Nuclear Plant One of the Most Troubled in Southeast
Emergency Shutdowns, Other Problems Continue at Shearon Harris

DURHAM, NC – A series of emergency reactor shutdowns and other persistent mechanical problems last year continued a troubling pattern for the Shearon Harris nuclear plant in southwestern Wake County, and led federal regulators to inspect the plant at a higher level than any other in the Southeast.  Watchdog organization NC WARN said today that the reactor shutdowns are far above the industry average, and the combination of problems is a reminder that attacks aren’t the only risks at nuclear power plants. 

The problems were revealed late last month when the U.S. Nuclear Regulatory Commission (NRC) gave its Annual Assessment Report for Harris at a meeting in nearby Apex, NC.  While the agency said that, “Overall, Harris operated in a manner that preserved public health and safety,” it noted a number of issues, several of them unresolved, that “degraded” the plant’s margin of safety.

In recent years, Harris has been plagued by emergency shutdowns due to a variety of human and mechanical problems.  In 1999, four emergency shutdowns – three in the first quarter alone – led to workers being “very disappointed … soul-searching” and unsure if the problems were “coincidental or a sign of a deeper problem,” according to The News & Observer.  (One of the four 1999 “SCRAMS” was later re-classified by plant owners as not an actual “shutdown,” although power was reduced to 3%.) NRC data indicates that the average nuclear plant experiences emergency shutdowns once every 18 months.

In addition, in April 2000, a safety monitoring system designed to provide vital information during an emergency failed for the 15th time since Shearon Harris began operating in 1987.  No published information is available as to the system’s operation since that time.

NRC records show that in January and July 2002, Harris staff performed manual reactor shutdowns due to equipment failures in the cooling system.  An automated shutdown then occurred in August when the outside power grid weakened. 

NC WARN Executive Director Jim Warren said today:  “Unfortunately, Progress Energy is far above the industry average in three important areas:  Emergency reactor shutdowns, required inspections, and the fact that it has interconnected the Harris reactor’s cooling system to four high-level waste pools – the nation’s largest.  Those are not distinctions we feel comfortable with.”  

Documents show that the other problems in 2002 included nine unresolved items identified during a triennial fire protection inspection by the NRC, including a “Severity Level III Notice of Violation.”  A follow-up inspection found corrective actions “not acceptable.”

Also, during an inspection, Harris employees found “rubber and other foreign material” clogging a cooling line in the heat removal system.  The NRC ranked the problem “low to moderate” in terms of safety significance. No penalties were assessed for any of Harris’s deficiencies.     

Also revealed last month:  Progress Energy said it has just replaced a number of evacuation sirens in the four counties within Harris’ 10-mile emergency planning zone.  In the past, the plant reported that many of its sirens were inoperable during severe weather.

In addition, due to a near-meltdown of the Davis Besse reactor in Ohio last year, which occurred after leaking control rod assemblies caused boric acid to burn a football-sized hole in the reactor vessel head, Progress Energy is required to perform a Bare Metal Inspection of the Harris reactor head to at an upcoming refueling outage to determine if leakage of borated water might be occurring.

It was at the NRC’s meeting that NC WARN openly called for plant manager Jim Scarola to take the one measure that could immediately lower risks of a catastrophic fire resulting from an attack: Lower the density of the racking of spent fuel assemblies in Harris’s cooling pools.  Such pools are considered the largest and most vulnerable targets at nuclear plants. 

Warren added, “Scarola dodged the question in front of the media by saying he wanted ‘to meet and discuss it.’  But now he’s stalling.  We want them to finally explain why shipping even more spent fuel to Harris – and creating an even larger disaster-in-waiting for the next several decades – is safer than hardening the storage at each of the corporation’s plants.”  Warren noted that research from Princeton and MIT indicates that Progress Energy could accomplish the risk reduction measures annually for less than the raise recently granted its CEO, William Cavanaugh.
##

Contact NC WARN:

North Carolina Waste Awareness and Reduction Network
P.O. Box 61051, Durham, NC  27715-1051
Ph: (919) 416-5077     Fax: (919) 286-3985


Unsubscribe from NC WARN Email